Planning Eginneer, SC COMPROIECT’92 SA Ploiesti, Cernavoda Nuclear Power Plant Project
prepare the integrated schedules using the information received from Engineering, Procurement and Construction departments.
- establishing, monitoring and controlling the Level 2 and 3 Project Schedules.
- advisse on matters that could prevent meeting project objectives.
- participate in the decision making process to optimizing overall planning performance.
- defining schedule objectives for the different Site Construction Contractors and support their planning and scheduling activities.
Professional Responsibilities
- To comply the overall Project Schedule with the establishment, monitoring and control of the time aspects using a computerized system of schedules.
- Produce Level 3 Integrated Schedules (three month window), including engineering, procurement, construction, commissioning and operation phases of the Project.
- To provide reports on a regular basis on the objectives set out for the Project specifying progress and deviations;
- To advise and propose solutions on all matters that could prevent meeting the objectives set out for the Project;
- To provide direction and liaison with all partners on the Project relative to Planning and Scheduling activities;
- To report on manpower, equipment, material and tooling requirements for the need of the Project;
- To assist and support all Departments in their planning and scheduling activities
- Company:
- Industry:
- Job Role:
- Project:
- Region:
- Skills & Expertise: