Senior Planner, ARCADIS Middle East, Hamad Medical City

START Date: 
February, 2015

The largest hospital facility in Qatar, 528 bed capacity and comprising up to10 floors of three building blocks with overall floor area of 214,000 sqm, cost QAR 2.4 billion. I worked for the clinet, Hamad Medical Corporation, on the project and also provided my services to Health Facility Department on other projects on part time basis. Key responsibilities on the projects are below.

  • ·         Development & monitoring of integrated programmes
  • ·         Design and implementation of project control tools and progress reporting to the project director
  • ·         FF&E programme development, monitoring and reporting
  • ·         Assisting project managers by producing individual department / facility program
  • ·         Review and analysis of contractor & sub-contractor programmes
  • ·         Writing programmes for Project Managers of different facilities/departments
  • ·         Creating What-If scenarios and presentation to the client