As a member of the project team, prepare schedule, monitored performance, and reported forecasts, trends, and scope change orders; assembled progress measurement reports; prepared cost and status reports for both internal and external client's use on Petro-Canada Dewax; Syneco Northern Lights; Enbridge Alberta Clipper; Fort Hills Terminal and Southern Lights projects.
Contributed to completion of a project close-out report containing cost, schedule and manpower and other pertinent informastion.
Managed well and pipeline tie-in program for Edson Area
Interfaced with Talisman Development, Drilling, Completions and Construction to monitor project costs and schedule to ensure the project success.
Created project schedules emphasizing key milestones of the project execution and held regular project meetings to monitor the progress of each project
Produced detailed cost estimate for the pipelines, facilities, man-hour estimates and deliverables summaries
Developed PFDs and P&IDs; responsible for checking plot plans, piping plans and isometrics