Project Controls Engineer

Project Controls Engineer, Oil Search Ltd, PNG-LNG

START Date: 
April, 2011

                                                                                               

Project Controls Engineer, ARCHIRODON CONSTRUCTION (OVERSEAS), Extension and Rehabilitation of port Jorf Lasfar

START Date: 
August, 2009

i'm working as a planning engineer (project controls Engineer) at Archirodon Overseas N.V Morocco branch. Working in two projects, off-shore sea outfall for a posphat factory and extension and rehabilitaion of Port Lasfar, El Jadida City.

Project Controls Engineer, ARCHIRODON CONSTRUCTION (OVERSEAS), Extension and Rehabilitation of port Jorf Lasfar

START Date: 
August, 2009

i'm working as a planning engineer (project controls Engineer) at Archirodon Overseas N.V Morocco branch. Working in two projects, off-shore sea outfall for a posphat factory and extension and rehabilitaion of Port Lasfar, El Jadida City.

Project Controls Engineer, ANSAQ Contracting Company, Multiple Project - Programs

START Date: 
July, 2008
END Date: 
September, 2014

•        Involve in program management, supporting different project managers handling different projects at the same timeline. Develop the schedule management plan and schedule design for the assigned projects, facilitate the development of master construction schedule.

Experience Hours (Planning & Scheduling): 
9000
Experience Hours (Cost Management): 
7000
Experience Hours (Forensic Analysis): 
2000

Project Controls Engineer, WorleyParsons, Oil & Gas, Infrastructure, Power

START Date: 
June, 2011

Working currenntly as a Project Controls Engineer with WorleyParsons in Mumbai

Project Controls Engineer, Thiess Pty Ltd, GORGON LNG Project

START Date: 
July, 1988

Project Controls Engineer, Thiess Pty Ltd, Perth Australia

On Gorgon Project at Barrow Island

I have started involving & Learning P6 last few months, found very interesting and challenging.

Updating the program with new WBS / Activities and Progresses on weekly basis to see the actual situation of the project.

Adjust the program (WBSs & Activities) on client priority basis to the restricted manpower on the project 

3 weeks, 6 weeks and Look Aheads to Construction Engineers to follow up with the construction activities.

Quanti

Project Controls Engineer, Thiess Pty Ltd, GORGON LNG Project

START Date: 
July, 1988

Project Controls Engineer, Thiess Pty Ltd, Perth Australia

On Gorgon Project at Barrow Island

I have started involving & Learning P6 last few months, found very interesting and challenging.

Updating the program with new WBS / Activities and Progresses on weekly basis to see the actual situation of the project.

Adjust the program (WBSs & Activities) on client priority basis to the restricted manpower on the project 

3 weeks, 6 weeks and Look Aheads to Construction Engineers to follow up with the construction activities.

Quanti

Project Controls Engineer, OHL Industrial Perú (Obrascon-Huarte-Lain), Camisea Second Expansion Project

START Date: 
March, 2012
END Date: 
August, 2012

Measurementand control of civil works, programming and project planning activities using specialized software (e.g. Primavera Project Planner P3/P6 and Microsoft Project), assessment of potential delays, cost control, preparation of interim applications for payment and review of subcontractor payment applications and production control.

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content