Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Zakum Development Company (ZADCO)

Project Management Advisor, Zakum Development Company (ZADCO), ZADCO UZ750 EPC2 Project

START Date: 
September, 2017
END Date: 
October, 2017
Management Advisor brought in to develop completion schedule for remaining construction, pre-commissioning and commissioning for the PBU-2A&B Milestones. Schedule was loaded with budget hours and quantities which were aligned with current installation rates and productivities.
Experience Hours (Planning & Scheduling): 
350

Snr Project Controls Specialist, Zakum Development Company (ZADCO), ZADCO UZ750 EPC2 Project

START Date: 
January, 2015
END Date: 
February, 2017

Snr Project Controls specialist on the ZADCO UZ750 EPC2 Fabrication phase for 3 Sub-contractors in the SEAsia & China region. Scope 12 Mechanical Technical Rooms (MTRs), 12 Modules (PAUs 10.5k MT), and 5 Electrical Buildings (MSS &  PGSS).

Responsible to the Snr Area Fabrication Manager for the region, the role provided the following:

Experience Hours (Planning & Scheduling): 
1500
Experience Hours (Cost Management): 
250
Experience Hours (Forensic Analysis): 
1000

Cost and Planning Engineer, Contracts Engineer, Chevron, Eni, Exxon, RasGas, Zakum Development Company (ZADCO), Various Projects in U.S., Central Asia, Middle East and Africa

START Date: 
April, 1982
END Date: 
December, 2015

I've held various roles in project controls and contract management in the international oil and gas industry; pls see my LinkedIn profile for details

Experience Hours (Planning & Scheduling): 
20000
Experience Hours (Cost Management): 
20000

fahimuddin Patel

First Name: 
fahimuddin
Last Name: 
Patel
Years Experience: 
45

Planning Assistant, Zakum Development Company (ZADCO), Site Major Works

START Date: 
August, 2008
  • Site Major Works Support and Execution assistance

 

Experience Hours (Planning & Scheduling): 
9950

1.“planning engineer”, Zakum Development Company (ZADCO), Upper Zakum Oil Field Development

START Date: 
May, 2006
END Date: 
October, 2006

 

Planning Engineer (Contract)

Zakum Development Company (ZADCO) Abu Dhabi                                  May 2006 -October 2006

On behalf of ADNOC and for the benefit of the shareholders in the joint venture, Abu Dhabi National Oil Company (ADNOC), ExxonMobil, and Japan Oil Development Company Ltd. (JODCO).

 

Key Project:

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content