Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Mining Works

Engineering Assistant, Fyaga, (various projects)

START Date: 
April, 2004
END Date: 
April, 2006
Responsible for the preparation of metered and basic engineering drawings. Reported to the project engineer.
Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
2000

Structural steel take-off controller, SSK Montajes e Instalaciones S.A.C., Gold Mill

START Date: 
January, 2007
END Date: 
April, 2007
 
Experience Hours (Planning & Scheduling): 
300
Experience Hours (Cost Management): 
0
Experience Hours (Forensic Analysis): 
0

Project Controls - Planner / Scheduler, Jacobs Perú S.A., Toromocho Mining Project (EPCM)

START Date: 
June, 2011
END Date: 
May, 2012
Project Controls -
Experience Hours (Planning & Scheduling): 
1800
Experience Hours (Cost Management): 
300
Experience Hours (Forensic Analysis): 
0

/ Construction Project Planner / Senior Planner, Barrick Gold Corporation – Barrick Exploraciones Argentina S.A., Pascua Lama Mining Project (Chile-Argentina) - EPCM

START Date: 
May, 2012
END Date: 
February, 2013
Project Controls -
Experience Hours (Planning & Scheduling): 
1500
Experience Hours (Cost Management): 
0
Experience Hours (Forensic Analysis): 
1000

Assistant Manager - Project Controls, Newfields, Buritica Mining Project

START Date: 
August, 2018
END Date: 
June, 2020
Project Controls
Experience Hours (Planning & Scheduling): 
2500
Experience Hours (Cost Management): 
1600
Experience Hours (Forensic Analysis): 
650

Project Controls Specialist, Ausenco, Mina Justa

START Date: 
October, 2017
END Date: 
August, 2018
Project Controls
Experience Hours (Planning & Scheduling): 
1650
Experience Hours (Cost Management): 
0
Experience Hours (Forensic Analysis): 
0

Project Controls - Planner / Scheduler, Amec Foster Wheeler Peru S.A., Lime & Limestone Plant Toromocho - EPCM

START Date: 
December, 2013
END Date: 
August, 2015
Project Controls -
Experience Hours (Planning & Scheduling): 
3300
Experience Hours (Cost Management): 
0
Experience Hours (Forensic Analysis): 
350

Head of Project Controls – Construction, Compañia de Minas Buenaventura, Tambomayo

START Date: 
September, 2015
END Date: 
June, 2017
Head of
Experience Hours (Planning & Scheduling): 
2500
Experience Hours (Cost Management): 
3500
Experience Hours (Forensic Analysis): 
1000

Civil Site Engineer, Biswas Engineering, Buildings

START Date: 
December, 2004
END Date: 
May, 2005
• Handled the preparation of daily & monthly progress report. • Developed & reviewed the project planning & progressing. • Reviewed the drawings, specifications and BOQ for speedy completion of work.
Experience Hours (Planning & Scheduling): 
400
Experience Hours (Cost Management): 
400

Janus Botha

First Name: 
Janus
Last Name: 
Botha
Professional Since: 
Jan-2000 (24.3 yrs experience)
Oldest experience: 
Jun 2010 (13.9 yrs experience, WARNING: 10.4 years variance with Professional Since)
Years Experience: 
10

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.