Logic Point Ltd. for Aker Solutions Senior Planner
START Date:
March, 2008
END Date:
April, 2009 Working on the Design, Procurement aspects in Portsmouth and then on the Construction at BP Chemicals Saltend Plant.
Firstly on a feasability study for the replcement of the Acid restructuring Project. Project shelved after FEED study.
Moved on to Vivergo Bio-Ethanol Plant Project, also at BP Chemicals, Saltend Hull. Utilising Primavera v 5 and co-ordinating contractors schedules to fit into Master Time Line schedule. Reassigned from Portsmouth to Site from October 2008 with responsibility for updating and monitoring Contractor Site Progress and Earned Value.
Firstly on a feasability study for the replcement of the Acid restructuring Project. Project shelved after FEED study.
Moved on to Vivergo Bio-Ethanol Plant Project, also at BP Chemicals, Saltend Hull. Utilising Primavera v 5 and co-ordinating contractors schedules to fit into Master Time Line schedule. Reassigned from Portsmouth to Site from October 2008 with responsibility for updating and monitoring Contractor Site Progress and Earned Value.
- Industry:
- Region: