Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Project Planning; Cost control; Budgeting; Performance Monitoring; Project Control; Risk Analysis; Claims; Resource allocation; Primavera P6

Senior Project Controls Engineer, Gurbag Group, HQ PMO. Entire Portfolio of Turkey

START Date: 
May, 2017
END Date: 
February, 2018

• Preparing the Baselines and updating project schedules based on field reports.

Experience Hours (Planning & Scheduling): 
800
Experience Hours (Cost Management): 
1300

Project Controls Lead, North West Construction, South Al Mutlaa Housing Project (Road and Infrastructure Works)

START Date: 
February, 2019

• Preparation of the baseline and up to date schedules in coordination with the Client.

Experience Hours (Planning & Scheduling): 
2400
Experience Hours (Cost Management): 
2400
Experience Hours (Forensic Analysis): 
300

Planning Manager, Telent UK, RETB Scotland (Radio Electronic Token Block)

START Date: 
July, 2014
END Date: 
November, 2015

Network Rail is in the process of replacing their current RETB radio system for the Far North and West Highland Lines in Scotland. After a life extension of infrastructure systems, the Next Generation RETB project is planning to Design, Manufacture, Test, Commission the replacement of the radio system element (NRN) as the frequencies used are due to be returned to OFCOM at the end of 2015.

Experience Hours (Planning & Scheduling): 
2350
Experience Hours (Cost Management): 
150
Experience Hours (Forensic Analysis): 
100

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content