Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Power Plant Construction

1.“planning engineer” or “project planner”, EDAC ENGINEERING LTD, Power Plant Construction

START Date: 
November, 2010
END Date: 
July, 2012
  • Planning of Each item of work as per available Resources and planning.
  • Responsible for Mechanical activities of project progress on planned vs. actual.
  • Conduct site inspection to update progress..
  • To coordinate & Report to Head Office and work for the direction.
  • Checking client documents, preparing deviation and clarification list.
  •  Preparation of Bill of Quantity.
  • Defining and updating the Project programmed.

Senior Manager Planning and controls, .., Power Plant Construction

START Date: 
July, 2000

Accomplished Mechanical Engineering with a flair forProject Management ,Material Management. Skilled in Project Management,Project Controls,Contracts,Cost Estimation, Material Management, Budgeting,Planning, Scheduling, Monitoring and Control, Resources planning and  well versed with Primavera P3V3, Primavera P3V5,Primavera P6V7(Enterprise) & MS Project.

A diligentworker with leadership qualities and team spirit

Senior Manager Planning and controls, .., Power Plant Construction

START Date: 
July, 2000

Accomplished Mechanical Engineering with a flair forProject Management ,Material Management. Skilled in Project Management,Project Controls,Contracts,Cost Estimation, Material Management, Budgeting,Planning, Scheduling, Monitoring and Control, Resources planning and  well versed with Primavera P3V3, Primavera P3V5,Primavera P6V7(Enterprise) & MS Project.

A diligentworker with leadership qualities and team spirit

Senior Manager Planning and controls, .., Power Plant Construction

START Date: 
June, 2012

Accomplished Mechanical Engineering with a flair forProject Management ,Material Management. Skilled in Project Management,Project Controls,Contracts,Cost Estimation, Material Management, Budgeting,Planning, Scheduling, Monitoring and Control, Resources planning and  well versed with Primavera P3V3, Primavera P3V5,Primavera P6V7(Enterprise) & MS Project.

A diligentworker with leadership qualities and team spirit

Senior Manager Planning and controls, .., Power Plant Construction

START Date: 
July, 2000

Accomplished Mechanical Engineering with a flair forProject Management ,Material Management. Skilled in Project Management,Project Controls,Contracts,Cost Estimation, Material Management, Budgeting,Planning, Scheduling, Monitoring and Control, Resources planning and  well versed with Primavera P3V3, Primavera P3V5,Primavera P6V7(Enterprise) & MS Project.

A diligentworker with leadership qualities and team spirit

Senior Manager Planning and controls, .., Power Plant Construction

START Date: 
June, 2012

Accomplished Mechanical Engineering with a flair forProject Management ,Material Management. Skilled in Project Management,Project Controls,Contracts,Cost Estimation, Material Management, Budgeting,Planning, Scheduling, Monitoring and Control, Resources planning and  well versed with Primavera P3V3, Primavera P3V5,Primavera P6V7(Enterprise) & MS Project.

A diligentworker with leadership qualities and team spirit

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content