1. HURL Fertilizer Proposal for Gorakhpur/ Sindri/ Barauni Project: LEPCC Duration: 36 Months
Project Engineering Man-hours: 1400000
Project Engineering LEPCC start Date: after LOA
Proposal planning as per ITB, GCC, SCC and contract documents
Development of complete project schedule and control mechanisms for the Dubin North Metro Project (at tender stage)
Set-up of complete project schedule and cost control system for the High Speed Rail link in Portugal.
KeyDuties:
· Preparation of various Procedures related to Planning and Project Management
· Defining the Project Breakdown Strategy.
· Contract and Change Management.
· Claim Management
Email: PPadmin@planningplanet.com