Project Planning and Control Manager, Toyo Engineering India Limited, Ethane Cracker Project

START Date: 
September, 2014

1.    HURL Fertilizer  Proposal for Gorakhpur/ Sindri/ Barauni Project: LEPCC Duration: 36 Months                

Project Engineering Man-hours: 1400000

Project Engineering LEPCC start Date: after LOA            

Proposal planning as per ITB, GCC, SCC and contract documents

Currently, I am working on Job stage Project planning and control engineer in HURL-Gorakhpur Project for L2, L4 Schedule in Primavera P6 V 17.12, Planning Procedures, Format finalization of Monthly/Weekly/ Bi-weekly Reports, DCI/MCI finalization, S-curve finalization, linking Progress curve and billing Schedule..

 

2.    FCHCU HPCL Proposal Project: EPC Duration: 30 Months                

Project Engineering Man-hours: 4,50,000

Project Engineering EPC start Date: after LOA            

Proposal planning as per ITB and contract documents

 

3.    Ethane Cracker Project:                                           EPC Duration: 48 Months                                                                        

              Project Cost: 8700 Cr                                             Engineering man-hours: 9,52,000

Project Engineering Start Date: 01-Jul-2014              Project End Date: 30-Jun-2018

Currently 100% engineering and Procurement completed and 95% construction completed.

 

Experience Hours (Planning & Scheduling): 
6000
Experience Hours (Cost Management): 
750