1. HURL Fertilizer Proposal for Gorakhpur/ Sindri/ Barauni Project: LEPCC Duration: 36 Months
Project Engineering Man-hours: 1400000
Project Engineering LEPCC start Date: after LOA
Proposal planning as per ITB, GCC, SCC and contract documents
Currently, I am working on Job stage Project planning and control engineer in HURL-Gorakhpur Project for L2, L4 Schedule in Primavera P6 V 17.12, Planning Procedures, Format finalization of Monthly/Weekly/ Bi-weekly Reports, DCI/MCI finalization, S-curve finalization, linking Progress curve and billing Schedule..
2. FCHCU HPCL Proposal Project: EPC Duration: 30 Months
Project Engineering Man-hours: 4,50,000
Project Engineering EPC start Date: after LOA
Proposal planning as per ITB and contract documents
3. Ethane Cracker Project: EPC Duration: 48 Months
Project Cost: 8700 Cr Engineering man-hours: 9,52,000
Project Engineering Start Date: 01-Jul-2014 Project End Date: 30-Jun-2018
Currently 100% engineering and Procurement completed and 95% construction completed.