Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

PROJECT PLANNER / SCHEDULER

Project Planner / Scheduler, Sandvik Mining & Construction Australia, Materials Handling Projects

START Date: 
April, 2011

Sandvik Mining & Construction Australia
1 Adelaide Terrace, Perth, WA, 6000
Australia

www.sandvik.com

klaus.backheuer@sandvik.com

Materials Handling Machines - Reclaimers, Stackers, Shiploaders, Conveyor systems

Project Planner / Scheduler

Experienced in Primavera P6, SureTrak, MS Project.

Profound Excel knowledge

Project Planner / Scheduler, Daewoo E&C, COmbined Cycle Power Plant

START Date: 
July, 2008

Planner / Scheduler

·         Understanding the Contract Scope of Work / Supply / Delivery / Execution.

·         Plan the projects form the Engineering stage to Supply and Construction as per the contract agreement.

·         Developing an Overall Master Time Schedule for the project (Tender submission / Awarded Projects).

PROJECT PLANNER / SCHEDULER, BOVIS LEND LEASE PHARMACEUTICAL PTE LTD, LBXS BIOREACTOR PLANT 2 PH 4

START Date: 
April, 2009
END Date: 
July, 2009

• Responsible for the revised Master Schedule for determining each activities category and classification including the location and

area requirements.

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content