PROJECT PLANNER / SCHEDULER, BOVIS LEND LEASE PHARMACEUTICAL PTE LTD, LBXS BIOREACTOR PLANT 2 PH 4

START Date: 
April, 2009
END Date: 
July, 2009

• Responsible for the revised Master Schedule for determining each activities category and classification including the location and

area requirements.

• Responsible for the preparation of monthly updates of Project Master Schedule that includes its Construction Schedule, Executive

Summary Schedule, Commissioning Schedule, Floor by Floor Schedule, Critical Path Schedule & the 8-Week Look-ahead

Schedule as well the Manpower Histogram.

• Responsible for the coordination with disciplines in monitoring its progress schedule.

• Evaluates and analyzes piping progress as provided by the disciplines supervisor and incorporated to piping S-Curve by the overall

progress completion, each pipeline system and each location.

• Perform other task as required by the Project Manager, Client’s Project Manager