Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

VOLKA

planner, volka, & Oil & Gas Projects 2) Buildings 3) Infrastructurus

START Date: 
October, 1989
END Date: 
September, 2013
Responsible for preparation of Clause 14 Baseline Program for project at the tendering stage Planning expertise

planner, volka, & Oil & Gas Projects 2) Buildings 3) Infrastructurus

START Date: 
October, 1989
END Date: 
September, 2013

Responsible for preparation of Clause 14 Baseline Program for project at the tendering stage as per the scope of

work in Primavera version P3.1  P6.

 Developed the (MTS) level 4 integrated EPC (Engineering, Procurement and Construction) schedule based on

contract requirements in cooperation with the Managing Contractor on Primavera.

Updated and reviewed the BSC (Balanced Score Card) for projects. Conducted several presentations for the

site team in order to highlight the importance of BSC.

4D Planner, Volka, 12 High Ends Residential/Condominiums Building Project

START Date: 
February, 1999
END Date: 
October, 2013

Responsible for preparation of Clause 14 Baseline Program for project at the tendering stage as per the scope of

work in Primavera version P3.1 & P6.

 Developed the (MTS) level 4 integrated EPC (Engineering, Procurement and Construction) schedule based on

contract requirements in cooperation with the Managing Contractor on Primavera.

Updated and reviewed the BSC (Balanced Score Card) for projects. Conducted several presentations for the

site team in order to highlight the importance of BSC.

chris william

First Name: 
chris
Last Name: 
william
Oldest experience: 
Oct 1971 (52.6 yrs experience, WARNING: 1.7 years variance with Professional Since)
Years Experience: 
28

4D Planning Consultant, Volka, Building Works (Villas)

START Date: 
October, 1996
END Date: 
October, 2013

Responsible for preparation of Clause 14 Baseline Program for project at the tendering stage as per the scope of
work in Primavera version P3.1 & P6.
 Developed the (MTS) level 4 integrated EPC (Engineering, Procurement and Construction) schedule based on
contract requirements in cooperation with the Managing Contractor on Primavera.
 Updated and reviewed the BSC (Balanced Score Card) for projects. Conducted several presentations for the
site team in order to highlight the importance of BSC.

planner, Volka, Building Projects

START Date: 
October, 1985
END Date: 
April, 2013

Responsible for the planning and control for the execution of a brown field development, including a field integrity upgrade and field capacity extension on an existing oil field in Oman. During the execution phase of involved in all project management related functions, including estimating, planning and scheduling, risk analysis, cost forecasting and economic appraisal.

AMIT PATEL

First Name: 
AMIT
Last Name: 
PATEL
Professional Since: 
Nov-2000 (23.4 yrs experience)
Oldest experience: 
Aug 2005 (18.7 yrs experience, WARNING: 4.7 years variance with Professional Since)
Years Experience: 
0

VOLKA Planner

START Date: 
August, 2005
Current Role

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content