Dubai Metro

Project Controls Manager, Parsons Brinckerhoff International, Dubai Metro

START Date
END Date

Responsible for the specification and implementation of a Master Projects Database (MPD), an earned value management (i.e. cost and schedule management) programme enterprise system to facilitate the co-ordination of works and projects between contractors and interfacing parties on London’s infrastructure and rail portfolio; £6.3 billion of infrastructure / system works.

Project Controls Engineer, JT Metro JV, Dubai Metro

START Date
END Date
  • Improved the procedure to control and monitor time aspect of the project. Created formats and charts for tracking key resources and manpower. Developed catch up schedules and mitigation programme to nullify or minimize delays, if any.
  •  
  • Improved payment certification procedure, which resulted in more amounts being certified by the Client. Initiated submission of detailed back up sheets and liaise with Engineers representatives.
  • Analyze the impact of variation instructions issued for the project. Manage earn values and generated S curves.

Planning Engineer, Parsons De Leuw Cather Overseas Ltd., Dubai Metro, Palm Jumeirah Gateway Bridge, Construction of Interchange 4.0.4.5.4.75,5.5.5 ,Emirates Road Widening, Sheikh Zayed Road Widening, Floating Bridge, Ras Al Khor Improvements, Business Bay

START Date
END Date

Preparing the Time Impact Analysis for Contractors,

Preparing Delay notifications,

Forensic Analysis using different methods like As Planned Impact Analysis, As Build Impact Analysis. Window Analysis

Preparing the Claim Programmes, Reviewing the Claim Programme.

Preparing Claim Documents i.e. Claim write ups organizing the claim in order of events.