Senior Planning Engineer

Senior Planning Engineer, Foster Wheeler, ARAMCO Diesel Hydro-treating DHT Project - RAS TANURA REFINERY

START Date: 
August, 2007
END Date: 
March, 2009

Responsibilities:

Participated in Technical bid evaluation and ensured submitted bids reflected best practice in accordance with Company’s Policies, Standards and Procedures (in UK).

Planning activities (in South Korea) of Approving and Maintaining the EPC Schedule, its updates, Milestones, Resources, Reports, Risks, Forecasts & Deliverables to achieve Project’s objectives.

Reviewed and Approved the Weekly Meetings, Monthly progress and Payment Certificates.

Senior Planning Engineer, Al Naboodah Construction Group, Comprehensive Improvements of the Parallel Roads- Phase 2A1, Jebel Ali Hills- Roads & Infrastructure, Satwa Zone S- Roads & Infrastructure

START Date: 
March, 2015
END Date: 
August, 2017

Currently at Al Naboodah as Senior Planning Engineer, working on a major residential infrastructure development project in Jebel Ali. 

Experience Hours (Planning & Scheduling): 
5600

Senior Planning Engineer, Kvaerner Engineering Norway, Norsk Hydro Oseberg Project

START Date: 
July, 1984
END Date: 
May, 1985

A member of the Project Surveillance team responsible for the planning and reporting function based at Stavanger Module Fabrication Site.

Experience Hours (Planning & Scheduling): 
1750

Senior Planning Engineer, Snamprogetti, Agip (UK) Tiffany Project

START Date: 
April, 1989
END Date: 
November, 1991

The project scope consisted of the Feasibility and Detail Design of AGIP (UK) North Sea Offshore Tiffany Project Topsides Facilities for Gas Compression, Power Generation and Utilities Modules.

Experience Hours (Planning & Scheduling): 
5100
Experience Hours (Cost Management): 
250

Senior Planning Engineer, British Gas Exploration and Development, South Morcambe Enhancement Project

START Date: 
November, 1991
END Date: 
May, 1994

The project scope consisted of the Design, Procurement, Fabrication and Construction with Offshore Hook-up of a Gas Compression / Switch and Control / Process Module built and and pre-commissioned by Degroot in Zwindrecht Olland

Experience Hours (Planning & Scheduling): 
4950
Experience Hours (Cost Management): 
200

Senior Planning Engineer, Abu Dhabi National Oil Company (ADNOC), Oil and Gas projects

START Date: 
July, 2005
END Date: 
December, 2010
Senior Planning Engineer Role includes Preparation of Project Master Schedules, Approve Baseline Schedules, Review Project Progress Reports and appraise Top Management on the status of the project. Review and approve Extension of Time claims and cost implications.

Senior Planning Engineer, Transfield Services Australia, Caltex Kurnell Refineries - Shut down, Turnaround and Reliability Projects

START Date: 
July, 2005
END Date: 
February, 2007

Planning and controls of reliability, shut down and maintenance operations at the various plants of the refinery including project scope definition, estimating, procurement planning, resource comntrol, reporting and progress tracking.

Experience Hours (Planning & Scheduling): 
1000
Experience Hours (Cost Management): 
1500
Experience Hours (Forensic Analysis): 
800

Senior Planning Engineer, KEO INTERNATIONAL CONSULTANTS, Day Care Center in Ahmadi, Kuwait

START Date: 
September, 1999
END Date: 
December, 1999

Project Planning & Scheduling, Variation evaluation, Review of Payment Applications, Time Extension analysis, Progress reports, Progress follow-ups.

Senior Planning Engineer, KEO INTERNATIONAL CONSULTANTS, Al Shaqab Equestrian Facility project, Education City Projects, Qatar

START Date: 
January, 2006
END Date: 
May, 2008

Senior Planning Engineer for the Al Shaqab Equestrian Facility project, Education City Projects interfacing with clients, design consultants, and Contractors, and other KEO divisions on ongoing projects. Responsibility also included analyzing and generating various reports, contractors claim analysis, updating risk register and conducting risk assessment meetings, conducting procurement meeting and preparing and for the project.