Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Senior Planning Engineer

Senior Planning Engineer, Darchem, Hinkley Point C EPR

START Date: 
September, 2020

Sept 2020 – to date                                                                                    Senior Planning Engineer                                                                 

Experience Hours (Planning & Scheduling): 
40000
Experience Hours (Cost Management): 
40000
Experience Hours (Forensic Analysis): 
850

Senior Planning Engineer, Darchem, Hinkley Point C EPR

START Date: 
September, 2020

Sept 2020 – to date                                                                                    Senior Planning Engineer                                                                 

Experience Hours (Planning & Scheduling): 
40000
Experience Hours (Cost Management): 
40000
Experience Hours (Forensic Analysis): 
850

Senior Planning Engineer, Balfour Beatty, Power Transmission Projects

START Date: 
November, 2018

Lead Project Planner 

Responsibilities are to develop an acceptable cost loaded baseline, project performance monitoring, application of EVMs on project, detailed volumetric related to project and proactive assessment of project status. I manage, revise, track and maintain status of the detailed project cost estimate/forecast to include all phases of project execution from design, procurement, survey, environmental and construction

Experience Hours (Planning & Scheduling): 
4800
Experience Hours (Cost Management): 
1950
Experience Hours (Forensic Analysis): 
600

Senior Planning Engineer, Thales Communications & Security (Hong Kong), C759 (KTE), C762 (SIL, KTE), MTR Contract Nos. C966 (SIL)

START Date: 
July, 2013
END Date: 
November, 2016
  • Preparation of Programmes and other schedule control systems required by Client prior to project construction.
  • Manage the progress updating of this reports  on a regular period as required by the Client
  • Prepare the Planning Sections of the PM Report to the Client
  • Provide support on tender preparation and submission.

Senior Planning Engineer, HSIN CHONG CONSTRUCTION (MACAU) LTD., Galaxy Resort and Casino – Phase 2

START Date: 
July, 2013
END Date: 
March, 2014
  • Management of the progress measurement system and the reporting set-up for the MEP Works’ Planning and Programme Management scope of the project.
  • See to it that these planning systems are implemented by the various MEP Sub-contractors.
  • Assist the MEP Sub-contractors so that they fully understand the planning methods and their progress reporting are concise and reliable.
  • Submit the required Reports to the Client’s MEP Planning Manager and establish close coordination with him to ensure that MEP Works are monitored and finished based on old or the new re-baselined

Senior Planning Engineer, Tekfen Construction and Installation Co., Al Khor Expressway Project

START Date: 
October, 2017


Employer: Public Works Authority (Ashghal)
Project Value: 7,600,000,000 QAR (2.1 B USD)

Project Description: The Project comprises the Design & Build of Al Khor Expressway [2 x 5 lanes approx. 33.65 km], 10 interchanges, full traffic model for year 2031, deep storm water tunnel [7.6 km + 1.25 km], intelligent transportation system (ITS), utilities [potable water, foul sewer, EHV, HV, MV, LV, TSE, UGN, QAF etc.], street lighting, road barriers, furniture and signage, landscaping etc.

Experience Hours (Planning & Scheduling): 
5200

Senior Planning Engineer, Capenhurst Nuclear Services, Various Nuclear Decommissioning

START Date: 
July, 2014
END Date: 
November, 2016

Capenhurst Nuclear Services (CNS), Capenhurst

Senior Planning Engineer

Responsible for providing planning support on various uranic material management and nuclear decommissioning and recycling projects, including earned value management, resource requirements and all other project control functions for reporting to senior management on NEC3 contracts.

Experience Hours (Planning & Scheduling): 
4800
Experience Hours (Cost Management): 
4800

Senior Planning Engineer, Wood Group PSN, Offshore Oil & Gas Platform Refurb

START Date: 
December, 2013
END Date: 
June, 2014

Wood Group PSN, Runcorn

Senior Planning Engineer

Employed on a short term contract where I was responsible to the JRE and senior management of level 4 FEED programmes, and level 2, 3 & 4 installation and commissioning & handover phases on various refurbishment projects on the North Sea offshore oil and gas platforms. Main responsibilities include provision of manpower histograms, performance s-curves and weekly reports to senior management.

Experience Hours (Planning & Scheduling): 
1150

Senior Planning Engineer, TechnipFMC, Energean Karish

START Date: 
October, 2017

Carrying Out Planning and Scheduling duties withing UK Operations Planning Dept.

Market Place

For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.
See how the TIME - LOCATION - VIEW brings clearness to your work programmes
Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.
Syndicate content