the team engagement and support of senior management are required but the sizes of required contingency reserves must be calculated and justified. Risk simulation helps with this.
Besides, risks are changing, performance may differ from expected, regular risk simulation helps to understand the real project status by estimating current probabilities of meeting project targets.
Member for
20 years 4 months
Member for20 years4 months
Submitted by Peter Holroyd on Fri, 2022-07-01 12:59
Member for
1 year 5 monthsPrimavera Risk Analysis is
Primavera Risk Analysis is widely used in industries that manage large, complex projects, especially in construction, engineering, and aerospace.
Thanks,
Member for
24 years 8 monthsPeter,the team engagement and
Peter,
the team engagement and support of senior management are required but the sizes of required contingency reserves must be calculated and justified. Risk simulation helps with this.
Besides, risks are changing, performance may differ from expected, regular risk simulation helps to understand the real project status by estimating current probabilities of meeting project targets.
Member for
20 years 4 monthsJohn,its the risk process
John,
its the risk process that important, the team engagement and support of senior management. The software doesn't really matter.
Member for
24 years 8 monthsJohn,just remember that all
John,
just remember that all of these tools are useless if your project has resource constraints and you level project resources.
Member for
9 years 8 monthsI could write a thesis on
I could write a thesis on this, but it is Sunday morning....
If you are an owner, looking for a long term, corporate wide, risk management strategy - Safran is the choice.
If you are a contractor, and you use MSP or P6 , Full Monte integrates easily and very quickly, at a price performance point that sets a new standard.
Member for
9 years 8 monthsI could write a thesis on
I could write a thesis on this, but it is Sunday morning....
If you are an owner, looking for a long term, corporate wide, risk management strategy - Safran is the choice.
If you are a contractor, and you use MSP or P6 , Full Monte integrates easily and very quickly, at a price performance point that sets a new standard.