Resource Allocation & baseline
Forum Sponsor
Top Posters
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Hunais M J
0 posts
Soheil Barekat
4 posts
Hi Asadullah
You assign resources to an activity in a programme.
You have to have the activities in place first.
When putting together a Bottom Up programme I set the durations at "best guess" based on my experience.
I then set up the resource modelling software to take the work load for each activity and the appropriate gang size.
This generates a resourced duration that over rides my original best guess.
Make sure that the resourced programme complies with your start and end dates in the contract.
This would represent your Planned resources.
If the work load or gang sizes change during progress you can change the resources in your baseline to replicate the anticipated effect on progress.
I hope this helps.
Best regards
Mike Testro