Schedule Risk and Schedule Risk Analysis Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Wed, 2009-04-29 06:18 Permalink RE: Resource Allocation & baseline Hi Asadullah You assign resources to an activity in a programme. You have to have the activities in place first. When putting together a Bottom Up programme I set the durations at "best guess" based on my experience. I then set up the resource modelling software to take the work load for each activity and the appropriate gang size. This generates a resourced duration that over rides my original best guess. Make sure that the resourced programme complies with your start and end dates in the contract. This would represent your Planned resources. If the work load or gang sizes change during progress you can change the resources in your baseline to replicate the anticipated effect on progress. I hope this helps. Best regards Mike Testro Log in or register to post comments
Member for 19 years 10 months Member for 19 years 10 months Submitted by Mike Testro on Wed, 2009-04-29 06:18 Permalink RE: Resource Allocation & baseline Hi Asadullah You assign resources to an activity in a programme. You have to have the activities in place first. When putting together a Bottom Up programme I set the durations at "best guess" based on my experience. I then set up the resource modelling software to take the work load for each activity and the appropriate gang size. This generates a resourced duration that over rides my original best guess. Make sure that the resourced programme complies with your start and end dates in the contract. This would represent your Planned resources. If the work load or gang sizes change during progress you can change the resources in your baseline to replicate the anticipated effect on progress. I hope this helps. Best regards Mike Testro
Member for
19 years 10 monthsRE: Resource Allocation & baseline
Hi Asadullah
You assign resources to an activity in a programme.
You have to have the activities in place first.
When putting together a Bottom Up programme I set the durations at "best guess" based on my experience.
I then set up the resource modelling software to take the work load for each activity and the appropriate gang size.
This generates a resourced duration that over rides my original best guess.
Make sure that the resourced programme complies with your start and end dates in the contract.
This would represent your Planned resources.
If the work load or gang sizes change during progress you can change the resources in your baseline to replicate the anticipated effect on progress.
I hope this helps.
Best regards
Mike Testro