Project Team and Responsibilities

4 replies [Last post]
moutaz aldeib
User offline. Last seen 1 week 6 days ago. Offline
Joined: 31 Dec 2003
Posts: 271
Groups: None

Hi,

who creates project team and defines the roles and responsibilities of the team? is it the Project Manager? in other meaning who develop RACI Matrix?

best

Replies

David Manna
User offline. Last seen 3 days 3 hours ago. Offline
Joined: 26 Nov 2017
Posts: 13
Groups: None

A responsibility assignment matrix (RAM), also known as RACI matrix /ˈreɪsiː/ or linear responsibility chart (LRC), describes the participation by various roles in completing tasks or deliverables for a project or business process. It is the duty of the project manager or person incharge. 

Zoltan Palffy
User offline. Last seen 22 hours 34 min ago. Offline
Joined: 13 Jul 2009
Posts: 1630

everyone in a management position who is working on the project should know the project requirements, But the PM should know them inside and out. 

moutaz aldeib
User offline. Last seen 1 week 6 days ago. Offline
Joined: 31 Dec 2003
Posts: 271
Groups: None

Thanks Zoltan, but what i understand is the proejct manager only as he/she is the one who fully understands the project requirements.

best,

muataz

Zoltan Palffy
User offline. Last seen 22 hours 34 min ago. Offline
Joined: 13 Jul 2009
Posts: 1630

upper management and the Project Manager