contract dispute

Dear All

In the tender document drawing few items only mention however in the Issue for construction drawing have mention few items but not indicated in the scope of works under the contract clause, Is it a variation order, please advise.

Regards,

Ronron

 

M
Mike Testro 👤 Member for 20 years 5 months

Hi Ronron

It all depends on the type of contract.

If you have a remeasurable BOQ then you get paid for the work you do the number of drawings is variable as the work progresses.

Anything else - such as fixed price - EPC - then you have a big problem without a clearly defined scopeof work.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts