Hi Ronron

It all depends on the type of contract.

If you have a remeasurable BOQ then you get paid for the work you do the number of drawings is variable as the work progresses.

Anything else - such as fixed price - EPC - then you have a big problem without a clearly defined scopeof work.

Best regards

Mike Testro