contract dispute

1 reply [Last post]
ronron martinez
User offline. Last seen 7 years 14 weeks ago. Offline
Joined: 19 Nov 2009
Posts: 41

Dear All

In the tender document drawing few items only mention however in the Issue for construction drawing have mention few items but not indicated in the scope of works under the contract clause, Is it a variation order, please advise.

Regards,

Ronron
 

Replies

Mike Testro
User offline. Last seen 4 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Ronron

It all depends on the type of contract.

If you have a remeasurable BOQ then you get paid for the work you do the number of drawings is variable as the work progresses.

Anything else - such as fixed price - EPC - then you have a big problem without a clearly defined scopeof work.

Best regards

Mike Testro