Constructive [overtime] acceleration - Opinions?

Member for

14 years 5 months

Thanks Mike/Daniel

Great info as always.

Regards

Aidan

Member for

24 years

Hi Aidan,

In adiition to Mikes' excellent advice, I think you need to play your cards well, by that I mean you need to build-up your case by documentation and keeping proper records of events, especially "excusable delays" mind you, not all excusable delays are compensable.

Regards,

Daniel

Member for

19 years 10 months

Hi Aidan.

If there is no acceleration clause in the contract AND the client has delayed the works AND the client insists that the original milestones be met THEN you have constructive acceleration.

In which case you will probably have a Time at Large situation.

The best route from here is to negotiate a change in the contract for an agreed acceleration cost and period - Time at Large puts the contractor in a strong negotiating position.

If that does not work then the contractor has a reasonable time to complete the works and the employer loses his right to LaD's - Penalties.

Best regards

Mike Testro