Conversion from MSP2007 to P7

Member for

20 years 5 months
Permalink

1. Import as an MPX/MPP.

2. Note and delete all headers that have been converted to activity descriptions - you notice them by the fact that theactivity typr becomes 'WBS Summary'

3. Change all other activities type from 'Resource Dependent' to 'Task Dependent' if you so wish

4. Check the calenders, links, constraints.

5. Schedule

NB: Ensure the activie MS Project is closed before you import.

 

Give me a shout if you get stuck - +447985252112

 

Regards

 

Ishmael