2. Note and delete all headers that have been converted to activity descriptions - you notice them by the fact that theactivity typr becomes 'WBS Summary'
3. Change all other activities type from 'Resource Dependent' to 'Task Dependent' if you so wish
4. Check the calenders, links, constraints.
5. Schedule
NB: Ensure the activie MS Project is closed before you import.
Vineet Simple way is to save
Vineet
Simple way is to save MSP file as XML . You will find this Option when you Click File->Save As .XML.
You can also do import setting in Primavera to get MSP data like Text 1 , Text 2 and other.
Untile Next Time
David Young
http://myprimavera.co.uk
david.young@myprimavera.co.uk
Conversion from MSP2007 to P7
1. Import as an MPX/MPP.
2. Note and delete all headers that have been converted to activity descriptions - you notice them by the fact that theactivity typr becomes 'WBS Summary'
3. Change all other activities type from 'Resource Dependent' to 'Task Dependent' if you so wish
4. Check the calenders, links, constraints.
5. Schedule
NB: Ensure the activie MS Project is closed before you import.