Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Revised Programme and changing start/finish with Global Change

No replies
Srdjan Kitanovic
User offline. Last seen 4 years 19 weeks ago. Offline
Joined: 3 Nov 2010
Posts: 2
Groups: None

There is some topic regarding changing the start/finish date with in the programme with global change, but I can`t find.

Programme has actual and keep all information regarding previous baseline (P6-programme is without attached baseline) I need to reschedule remained not started activities, moving them backward.

Please give me the link or global change steps.

Thanks in advance

Srdjan