If all 10 blocks are the same and all start and end on the same date and all blocks are on the same programme then they would be either all critical or none.
I suggest you stagger the start date by linking excavation complete from block A to Block B and so on.
This will put a critical path through the project by way of a resource driven linkage.
Avoid using Must end On constarints to set up false criticality.
I am very well aware of critical path concept. What i did was simply planned for one block in every aspect. It showed the critical and non critical activities as per actual expectations. Then i copied the wbs to other blocks. Then Linked each block to the start and finish milestone of the project, Yet it is showing all the activities non critical. Please help
Member for
12 years 8 monthsThankyou Mukund ji
Thankyou Mukund ji
Member for
19 years 10 monthsHi Punit If all 10 blocks are
Hi Punit
If all 10 blocks are the same and all start and end on the same date and all blocks are on the same programme then they would be either all critical or none.
I suggest you stagger the start date by linking excavation complete from block A to Block B and so on.
This will put a critical path through the project by way of a resource driven linkage.
Avoid using Must end On constarints to set up false criticality.
Best regards
Mike Testro
Member for
12 years 8 monthsDear Mukunda Ji,I am very
Dear Mukunda Ji,
I am very well aware of critical path concept. What i did was simply planned for one block in every aspect. It showed the critical and non critical activities as per actual expectations. Then i copied the wbs to other blocks. Then Linked each block to the start and finish milestone of the project, Yet it is showing all the activities non critical. Please help
Member for
16 years 11 monthsDear punit if u know critical
Dear punit
if u know critical path concept u can understand why the software s not giving the critical path. It depends on ur input( links, constraints etc..)
Thanks & Regards
Mukunda