Planning and Scheduling related problem

Member for

12 years 8 months

Thankyou Mukund ji

Member for

19 years 10 months

Hi Punit

If all 10 blocks are the same and all start and end on the same date and all blocks are on the same programme then they would be either all critical or none.

I suggest you stagger the start date by linking excavation complete from block A to Block B and so on.

This will put a critical path through the project by way of a resource driven linkage.

Avoid using Must end On constarints to set up false criticality.

Best regards

Mike Testro

Member for

12 years 8 months

Dear Mukunda Ji,

I am very well aware of critical path concept. What i did was simply planned for one block in every aspect. It showed the critical and non critical activities as per actual expectations. Then i copied the wbs to other blocks. Then Linked each block to the start and finish milestone of the project, Yet it is showing all the activities non critical. Please help

Member for

16 years 11 months

Dear punit

 

if u know critical path concept u can understand why the software s not giving the critical path.  It depends on ur input( links, constraints etc..)

 

Thanks & Regards

Mukunda