Primavera P6 schedule % complete not calculated

Member for

12 years 4 months

for activities. schedule % complete is calculated using the following formula:

Schedule % Complete(Act) = ( [Data Date] – [Baseline Start] ) / ( [Baseline Finish] – [Baseline Start] )

as you see the above formula is not related to the cost of the activity but
for wbs elements schedule % complete is calculated using the following formula

schedule % complete = pv/bac

as you see the above formula is related to the cost of the wbs element

so if the cost of a wbs element is 0 u get 0 for schedule % complete

if u want to have a good grasp of the issue read the following link:

http://www.plannertuts.com/primavera-p6-tutorials/primavera-p6-schedule-percent-complete-guide-1-1180/

Member for

12 years 9 months

Thank Alexandre.

i didnt use Duration % complete field. now is ok. But why rhe Schedule % complete is 0??

thank

 

Member for

22 years 9 months

Hi Antonio,

open the View, Group and Sort dialog box

check the Show Group Totals option

also make sure you are using the Duration % complete field and not the Activity % complete

Alexandre