Oracle Primavera - PM6 Member for 15 years 11 months Member for 15 years 11 months Submitted by Raymund de Laza on Fri, 2012-12-21 06:12 Permalink Luke, Copy your original Luke, Copy your original duration into a UDF then display it. Then change the default calendar with 7 days working days. Now you can see both working n calendar days. Hope this will help. Merry Christmas.... Log in or register to post comments
Member for 15 years 11 months Member for 15 years 11 months Submitted by Raymund de Laza on Fri, 2012-12-21 06:12 Permalink Luke, Copy your original Luke, Copy your original duration into a UDF then display it. Then change the default calendar with 7 days working days. Now you can see both working n calendar days. Hope this will help. Merry Christmas....
Member for
15 years 11 monthsLuke, Copy your original
Luke,
Copy your original duration into a UDF then display it.
Then change the default calendar with 7 days working days.
Now you can see both working n calendar days.
Hope this will help.
Merry Christmas....