Limited sharing: erase relationships without affecting the dates

Member for

16 years 7 months

3) SNET = Start No Earleir Than

4) You can use the "Update progress" tool, to make everything complete. Takes less than a minute.

 

Have you actually checked that a programme without any links will be acceptable? Also: why are you so reluctant to share the links? 

Member for

15 years 11 months

As Gary say,

1. Use Start on or After Constriant. then delete links

2. Make all activities compelete by using Update Progress with data date at the end of project. Then delete links

Member for

13 years

Gary,

1) Print as pdf -this will maintain the dates, but you will struggle to show all other info in a legible view (costs, activty codes, early & late dates, float, constraints, etc):I need to submit the Primavera file, a pdf is not allowed.

2) Ensure "schedule automatically when a change affects the dates" option from schedule options is not checked, then delete the relationships. All the dates will be maintained until/unless you hit F9:This is being undone when I am saving the file.

3) Give all activities a SNET constraint  = early start date, then delete the relationships.: A SNET is something I cannot find amonst the possibilities in the constraints

4) Make all actvities complete, then delete the relationships:This will take way too long...

 

Do you have another idea?

Thanks for the replies guys!

 

Member for

13 years

I have to submit the file as a Primavera file, so a pdf is not an option.
Would have been a nice solution though.

Member for

16 years 7 months

In order of simplicity, your options are:

 

1) Print as pdf -this will maintain the dates, but you will struggle to show all other info in a legible view (costs, activty codes, early & late dates, float, constraints, etc).

2) Ensure "schedule automatically when a change affects the dates" option from schedule options is not checked, then delete the relationships. All the dates will be maintained until/unless you hit F9.

3) Give all activities a SNET constraint  = early start date, then delete the relationships.

4) Make all actvities complete, then delete the relationships.

Member for

19 years 10 months

Hi Ward

Perhaps you can book it out in electronic format but with no edit rights.

Best regards

Mike Testro

Member for

15 years 11 months

Ward,

Just Print it in PDF file.