Oracle Primavera - PM6 Member for 24 years 6 months Member for 24 years 6 months Submitted by Paul Harris on Wed, 2012-10-10 11:51 Permalink TomHave you any blank lines, Tom Have you any blank lines, if so remove them before saving as a XML file, this in my experiance is a show stoper for importing into P6. If you want to see the issues when importing a MSP file into P6 there is a Technical paper on my websites. Paul E Harris Eastwood Harris Pty Ltd www.eh.com.au, www.eastwoodharris.com and www.primatrain.com.au Project Control Consultants and Planning and scheduling software book and training manual publishers Log in or register to post comments
Member for 24 years 6 months Member for 24 years 6 months Submitted by Paul Harris on Wed, 2012-10-10 11:51 Permalink TomHave you any blank lines, Tom Have you any blank lines, if so remove them before saving as a XML file, this in my experiance is a show stoper for importing into P6. If you want to see the issues when importing a MSP file into P6 there is a Technical paper on my websites. Paul E Harris Eastwood Harris Pty Ltd www.eh.com.au, www.eastwoodharris.com and www.primatrain.com.au Project Control Consultants and Planning and scheduling software book and training manual publishers
Member for
24 years 6 monthsTomHave you any blank lines,
Tom
Have you any blank lines, if so remove them before saving as a XML file, this in my experiance is a show stoper for importing into P6.
If you want to see the issues when importing a MSP file into P6 there is a Technical paper on my websites.
Paul E Harris
Eastwood Harris Pty Ltd
www.eh.com.au, www.eastwoodharris.com and www.primatrain.com.au
Project Control Consultants and Planning and scheduling software book and training manual publishers