If I understand you correctly, you are saying that when you enter a finish date of 15AUG, P6 automatically gives you the finish time of 00:00. This is the way P6 used to work before Version 6.
Either way – this should not be a problem. When you enter the actual Start or Actual Finish dates, you should also supply the finish time as well as the date. P6 stores all dates as both date and time. It does not matter how you display it, the time is entered so for accuracy’s sake you should always show and enter the time as well as the date. Good luck!
Check for the hours per time period assigned to the calendar for the activity. From your query it's clear that you are working 7 hrs a day. So, please ensure that the same 7 hrs/day has been set in the "Time Periods" setting of the particular calendar.
Member for
22 years 9 monthsMelbin, If I understand you
Melbin,
If I understand you correctly, you are saying that when you enter a finish date of 15AUG, P6 automatically gives you the finish time of 00:00. This is the way P6 used to work before Version 6.
Either way – this should not be a problem. When you enter the actual Start or Actual Finish dates, you should also supply the finish time as well as the date. P6 stores all dates as both date and time. It does not matter how you display it, the time is entered so for accuracy’s sake you should always show and enter the time as well as the date. Good luck!
Member for
14 years 8 monthsDear Melbin,Check for the
Dear Melbin,
Check for the hours per time period assigned to the calendar for the activity. From your query it's clear that you are working 7 hrs a day. So, please ensure that the same 7 hrs/day has been set in the "Time Periods" setting of the particular calendar.
Regards,
Kaif