Procurment Weight Factor problems..

Member for

14 years 1 month
Permalink

hi hanson,
 
On activities you could use activity steps with a specific weight and add comments if needed.
 
Or use WBS milestones when you have your schedule organised in a WBS structure. 
Milestones are assigned at the WBS level, and each milestone is given a weight that indicates its importance to the project schedule. When you mark a WBS milestone as complete, the module uses its weight to calculate the performance percent complete of all activities included in the WBS level. That is, the performance percent complete is applied to all activities under that WBS level and then rolled back up to the WBS.
To redo the whole process when products are not accepted simply copy the activity or wbs node from a copy of your project or make templates.
Regards,
Arend

Member for

13 years 9 months
Permalink

Vladimir,
 
Thank you very much I will think about this idea and ask our clint.

Member for

24 years 8 months
Permalink

I would apply weight to Acceptance milestones.If not accepted percents are not earned and additional activities are required.In Spider Project we call it conditional scheduling.