Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Baseline to Actual Update

1 reply [Last post]
Bert Ella
User offline. Last seen 10 years 14 weeks ago. Offline
Joined: 16 Feb 2011
Posts: 21

Dear Experts,

 

Situation:

i am updating the program in weekly/mothly basis but i am not assigning nor maintaining the baseline for so long..

the question is how can i include/assign or maintain the original baseline to the latest updated program??

please help sirs..

 

Thanks and Regards,

HBS

Replies