Baseline to Actual Update

Member for

22 years 9 months
Permalink

Bert,

it was a big mistake not to maintain a baseline since before the 1st update!

you can maintain and assign a baseline at any time; you will baseline the current status of the project, the original project is lost for good, unlesse you have printed or exported it before the 1st update!

Hope it helps,

Alexandre