Baseline value = is similar to a benchmark that shall never move or change prior, during or after the execution of work.
Budget value = is equal to Baseline value prior to execution of work, and when the work progresses it is equal to required value within the remaining duration.
You will notice that Budget, Baseline and Remaining Values are all equals prior to execution of work.