Thank you very much for your replay. I was wondering how it's possible to fit in my EPC project, if I need to monitor %progress for overall and each EPC phase using multi weight crieteria ( manhours , money, physical progress) at different phases? I use sure trak.
Hope you come forward to help me in this issue with my great thanks.
Hanson
Member for
15 years 11 months
Member for15 years11 months
Submitted by Raymund de Laza on Mon, 2012-04-30 13:13
Member for
13 years 9 monthsSir,Thank you very much for
Sir,
Thank you very much for your replay. I was wondering how it's possible to fit in my EPC project, if I need to monitor %progress for overall and each EPC phase using multi weight crieteria ( manhours , money, physical progress) at different phases? I use sure trak.
Hope you come forward to help me in this issue with my great thanks.
Hanson
Member for
15 years 11 monthsHanson, Can you make it clear
Hanson,
Can you make it clear for me if that term "Milestone" as you mentioned is the the same as the Baseline program.
I understand that milestones can never be loaded with resources.
Please Clarify.
Regards,