Thanks Alexandre,
 
I have every possible option of auto compute actuals turned on, both at activity level and resource level.
Cannot find an option for this at project level.......
Thanks Alexandre,
 
I have every possible option of auto compute actuals turned on, both at activity level and resource level.
Cannot find an option for this at project level.......
Thanks Alexandre, I have
Thanks Alexandre,
 
I have every possible option of auto compute actuals turned on, both at activity level and resource level.
Cannot find an option for this at project level.......
Thanks Alexandre, I have
Thanks Alexandre,
 
I have every possible option of auto compute actuals turned on, both at activity level and resource level.
Cannot find an option for this at project level.......
Andy,did you tick Autocompute
Andy,did you tick Autocompute Actuals at project level?check your resources, Autocompute should be ticked on there tooAlexandre