P6 Calculation of actual units/costs

3 replies [Last post]
Andy McShane
User offline. Last seen 8 years 15 weeks ago. Offline
Joined: 3 Oct 2003
Posts: 6
Groups: None

Can anyone out there explain why P6 (7.0) doesnt alway calculate actuals....?????

This is driving me crazy! 

Yes, auto compute actuals is ticked on and costs are calculated from Units

 

 

Replies

Andy McShane
User offline. Last seen 8 years 15 weeks ago. Offline
Joined: 3 Oct 2003
Posts: 6
Groups: None

Thanks Alexandre,

 

I have every possible option of auto compute actuals turned on, both at activity level and resource level.

Cannot find an option for this at project level.......

Andy McShane
User offline. Last seen 8 years 15 weeks ago. Offline
Joined: 3 Oct 2003
Posts: 6
Groups: None

Thanks Alexandre,

 

I have every possible option of auto compute actuals turned on, both at activity level and resource level.

Cannot find an option for this at project level.......