If there are links, they can not be deleted during schedule.
If a logic is not respected, it must come from wrong links applied to your predecessors.
Lets imagine that you have 3 activities in FS
[[wysiwyg_imageupload:999:]]
After your update, acitivty B is declared as completed while A is on going. Thus even if activity C is linked to B, it will not before completion of A.
[[wysiwyg_imageupload:1000:]]This could be one reason.
Nevertheless, you can use "Mandatory contraint", but this clearly not a good practice in my mind.
It is hidding your logic or mistake as identified here above,
Member for
19 years 7 monthsHi Kate,If there are links,
Hi Kate,
If there are links, they can not be deleted during schedule.
If a logic is not respected, it must come from wrong links applied to your predecessors.
Lets imagine that you have 3 activities in FS
[[wysiwyg_imageupload:999:]]
After your update, acitivty B is declared as completed while A is on going. Thus even if activity C is linked to B, it will not before completion of A.
[[wysiwyg_imageupload:1000:]]This could be one reason.
Nevertheless, you can use "Mandatory contraint", but this clearly not a good practice in my mind.
It is hidding your logic or mistake as identified here above,
Regards