Problem with relationships to completed/in progress tasks

Member for

19 years 7 months

Hi Kate,

If there are links, they can not be deleted during schedule.

If a logic is not respected, it must come from wrong links applied to your predecessors.

Lets imagine that you have 3 activities in FS

[[wysiwyg_imageupload:999:]]

After your update, acitivty B is declared as completed while A is on going. Thus even if activity C is linked to B, it will not before completion of A.

[[wysiwyg_imageupload:1000:]]This could be one reason.



Nevertheless, you can use "Mandatory contraint", but this clearly not a good practice in my mind.

It is hidding your logic or mistake as identified here above,

Regards