Asssigning Baselines with Actual Dates

Member for

21 years 2 months

Thanks Gary & Raymund. Much appreciate your tips.

Nith

Member for

15 years 11 months

Nith,

Restore your PB, open it, and execute Global change to make the Planned Dates = Current Dates.

Re attach PB into CP, assign again as PB. 

Member for

16 years 7 months

This is a common problem, and to my mind one the most stupid default setting in the history of planning software

 

Go to admin > admin preferences > earned value tab, and select either " at completion values with current dates" or "budget values with current dates"

It's probably also worth going to project > calculations and ensuring the "link budget and at completion for not started activities" box is ticked -another stupid default setting.

 

For more info on what these settings do, Paul Harris has a brief presentation on the issue on his website:

http://www.eh.com.au/Technical%20Papers/110616_P6_V7_What_Baseline_Bars_am_I_Displaying.pdf