This is a common problem, and to my mind one the most stupid default setting in the history of planning software
Go to admin > admin preferences > earned value tab, and select either " at completion values with current dates" or "budget values with current dates"
It's probably also worth going to project > calculations and ensuring the "link budget and at completion for not started activities" box is ticked -another stupid default setting.
For more info on what these settings do, Paul Harris has a brief presentation on the issue on his website:
Member for
21 years 2 monthsThanks Gary & Raymund. Much
Thanks Gary & Raymund. Much appreciate your tips.
Nith
Member for
15 years 11 monthsNith, Restore your PB, open
Nith,
Restore your PB, open it, and execute Global change to make the Planned Dates = Current Dates.
Re attach PB into CP, assign again as PB.
Member for
16 years 7 monthsThis is a common problem, and
This is a common problem, and to my mind one the most stupid default setting in the history of planning software
Go to admin > admin preferences > earned value tab, and select either " at completion values with current dates" or "budget values with current dates"
It's probably also worth going to project > calculations and ensuring the "link budget and at completion for not started activities" box is ticked -another stupid default setting.
For more info on what these settings do, Paul Harris has a brief presentation on the issue on his website:
http://www.eh.com.au/Technical%20Papers/110616_P6_V7_What_Baseline_Bars_am_I_Displaying.pdf