Importing Resource Assignments

10 replies [Last post]
Jon Ward
User offline. Last seen 9 years 20 weeks ago. Offline
Joined: 16 Jun 2008
Posts: 60

Hi all - ANY advice would be very much appreciated,,,

I am currently running imports into P6 (from an xls workbook) that give me both Activities and Resource Assignments, my question is this – is there a method of OVER-WRITING the resources during the import, to be more specific – if ACTIVITY001 has a resource of ‘electrician’ and for what ever reason the activity has been changed (in the xls import file) to be ‘pipe fitter’, following my import ACTIVITY001 will have both ‘electrician’ & ‘pipe fitter’ (‘electrician’ will be the primary resource), I just want the new import to overwrite the current resource if that makes sense??

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 1 day ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

you have 2 options 

option #1

delete ALL of the existing resources and import new

option #2 

export all activites with resources then in excel do a vlookup to compaire the existing to the new and if it is not found delete the resource by putting a Y in the last column that is exported 

Marie John
User offline. Last seen 5 years 4 weeks ago. Offline
Joined: 25 Mar 2019
Posts: 2
Groups: None

We have good and expert team for best assignment help. contact us now and get good grades in your assignment.

Raymund de Laza
User offline. Last seen 31 weeks 4 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Jon,

You are Welcome.

Here is how to On - Off Limit line. Uncheck "Show Limit"

 

973
limit_2.jpg

Jon Ward
User offline. Last seen 9 years 20 weeks ago. Offline
Joined: 16 Jun 2008
Posts: 60

sorry Raymund - this shall be the last question, how do i turn the limit line on and off? i.e. make it visable,, i have looked through the Activity Usage Profile options and cannot see it anywhere?

 

many thanks

 

Jon

Jon Ward
User offline. Last seen 9 years 20 weeks ago. Offline
Joined: 16 Jun 2008
Posts: 60

thanks again Raymund - excellent help!!

Raymund de Laza
User offline. Last seen 31 weeks 4 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Jon,

Here is the excel window.

971
resource.jpg

 

 

For the Resource Limit modify the Max Unit per Time to show the limit line on the profile.

972
limit.jpg

Anning Sofi
User offline. Last seen 5 years 38 weeks ago. Offline
Joined: 22 Jan 2012
Posts: 89
Groups: None
 

(here is Primavera's help info on deleting row in  the import worksheet.)

 

Delete Project data in the XLS file

To delete project data using Microsoft Excel, place a 'D' or ' d' in the Delete This Row column for the selected row in the worksheet. When importing, the information included in the deleted row will be removed from the project.

Jon Ward
User offline. Last seen 9 years 20 weeks ago. Offline
Joined: 16 Jun 2008
Posts: 60

also Raymund,

(apologies for the continual questions), how do i set a horizontal line that details the limit that I would like to set for the resources within the Activity Usage Profile view in P6,, i currently view BUdgeted Labor Units, Actual and Remaining as a traditional bar-chart however I would like to see a horizontal line across that I can use to level against (manualy before I sutomatically level)

 

Once again, many thanks

 

JOn

Jon Ward
User offline. Last seen 9 years 20 weeks ago. Offline
Joined: 16 Jun 2008
Posts: 60

Thank you Raymund,

What is the name of the field/column that I need to insert the 'Y' (for deletion) into? is this field/column on the TASKRSRC tab of the import workbook? I import both TASK and TASKRSRC in order to update all of my fields.

 

Once again, many thanks

 

Jon

Raymund de Laza
User offline. Last seen 31 weeks 4 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Jon,

In excel, Use the rightmost column to delete the existing ("Y") then copy the same activity to another row for the new resource. Then import.

Hope this will help.