Thanks Raymund,

Actually I am doing that by using UDF and Global Chang taking into consideration that the finish progress bar shuold be based on the the schedule %.But I was looking for an easier way.

Regards,

Member for

15 years 11 months

Ayman,

Baseline Progress Bar is not available in P6 in my opinion.

However if you want to show using the UDF, create UDF say Min (From or Start Date) and Ali (To or Finish Date).

On the bar option, create a Bar Name - BL Progress, Timescale - User Dates, then select the UDF for User Start Date and Use Finish Date. On the Bar Style - make the style & row the same as your baseline Bar.

Hope this will help.

Member for

13 years 11 months

Hi,

right click in the bar area,  select the baseline bar and close. you will see it.

regrds,

kk

Member for

14 years 10 months

Raymund,

I could not see the attached picture ,however I'd like to show the blue bar on the baseline bar as we used to get it from P3,on other words, to show the planned progress on the baseline bar.

I am aware that it can be done by the user define fields,but it is lettle bit complicated,like to get an easy way.

Thanks for reply,regards,

Member for

15 years 11 months

Ayman,

Do you mean similar to this?