Converting Project Activity Codes to EPS codes

3 replies [Last post]
SSA Zaidi
User offline. Last seen 12 years 8 weeks ago. Offline
Joined: 1 Mar 2012
Posts: 2
Groups: None

Hi

i have run into a new problem. I created a project with project activity codes(P6.2) . now i want to use the same codes for other projects in the same eps, so i tried to conver them to the EPS codes.

As soon as a project activity codes are converted to EPS codes, i loose their existing allocation in the project and my project becomes void of codes allocation.

 

is there any way around it?

 

Regards

Replies

Alfredo Jr. Hubilla
User offline. Last seen 4 years 40 weeks ago. Offline
Joined: 6 Feb 2012
Posts: 20

When you make the activity codes to EPS codes, make sure you create a copy of that activity codes from the Project and that newly copied activity codes you can convert it to EPS codes and put it to your new project.

 

Hope this will help.

Raymund de Laza
User offline. Last seen 31 weeks 5 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Hi,

I think your problem is relative to Group & Sort By.

Right Click on Projects window select Group & Sort By - Organized the projects accordingly.

 

Hope this will help

Frederic Fasquelle
User offline. Last seen 1 year 10 weeks ago. Offline
Joined: 16 Mar 2006
Posts: 61

Hi,

When you create EPS code, this belongs to node.

Projects you have created must be below this node.

Regards