P6v7 - Export / Import Change in Dates

Member for

13 years 9 months

We had the same experience as your case mentioned. ; the consultant import did not match fully the dates of the main contractor dates after import of the .xer file

What happened was the main contractor made few changes to the calendar (working days in some months, and working hours in one month). After export, the consultant imported the file; after import, some date discrepancies was found with the main contractor dates, in reference to a hard copy the main contractor programme.

To troubleshoot the problem,  consultant made the following exercies:

1) changed and tested the various import options in P6 v 7; -> (didn't solve the issue)

2) matching the P6 user and admin settings for both contractor and consultant.  -> (didn't sove the issue)

3) ensuring both default calendars at the same -> (didn't solve the issue)

At the end, the consultant has sit in the main contractor computer to manually verify/ copy the calendar settings of main contractor;  (working days per month, working hours per day, holidays etc). - THIS WORKED.

 

The lesson to this:

The P6 options in importing to update calendar of an existing programme do not necessarily give a 100% exact copy.  By import update options, I mean a) Update Existing; or b) Insert new c) Delete

(Also the programme in this case involved 20,000+ activities, 44,000 relations, 2 calendars, progressed and updated).

 

 

I hope this solution will work on your case also. Maybe also, there are other solutions.

Good Luck.

 

Member for

24 years

Hi Deepak,

P6 has Global, Resource and Project calendars, Global Calendar is applicable to all your projects, Resource Calendar is used for specific activities within a project and Project calendar is used exclusively for a project. When you set-up your calendar, first you set it up under global calendar and then make it project specific by adding it to your project or you can do it vice versa. Normally, when you export the P6 file, the project calendar data should come with the XER file, unless you defined it as global and did not make it project specific.

Regards,

Daniel

Member for

14 years 5 months

Thanks everyone for reply.

 

Ronald, There are no resources in the schedule & client is using the same calendars at project level. Dates appears to be fine only until they press F9 and then it goes out with some tasks at – var of 18-20 days

 

Ferdinand, I checked admin preferences on both M/c’s and they are similar

 

Raymund, Default calendar on both M/c’s are same. I thought default calendar setting only relates to insertion of new task , and on scheduling P6 perform calculations on basis of individual task calendar (only variation being the Lag as per scheduling options )

Member for

18 years 3 months

check also ADMIN PREFERENCES timeperiods

Member for

22 years 9 months

The last time I saw this, the problem was in matching the resources.  They need to be using the same calendars and resource rules.  A single resource rule that does not match can drastically change the activity dates.  Good luck!

Member for

15 years 11 months

Hi Deepak,

I suggest to set the Default calendar of your client machine to be the same as your Default Calendar.

Member for

14 years 5 months

Thanks Daniel. Let say you got multiple calendars with 8Hr/d (Design), 10 Hr/d (Execution) and 24Hr/d (facility shutdown) but on a global level , the default in P6 is 8Hr/d. Client machine also shares the similar setting of 8Hr/d as default. 

So, in this case what (calendar settings) gets exported and import back on multiple machines ? My assumption was "Hours per time period" other then generic is calendar specific and should be exported as part of xer.

Does this mean if a project has 10 different calendars then on import, client has to check "Hours per time period" for each of them ?

R,

Deepak

Member for

24 years

Hi Deepak,

I believed it has something to do with the set-up of 'Hours Used Per time Period', P6 calculates in hours and the standard working hours per day in P6 is 8 hours = 1 day and the moment you change this and the other computer is not configured ths same way then obviously you will have a variance. 

Regards,

Daniel