I think I'm having the same problem. I move the data date, run "update progress" and the activies highlighted move out in time to the new DD. It doesn't do this on all projects but just one right now.
ANY advise on what to configure to get this working correctly again will be GREATLY appreciated.
Member for
13 years 2 monthsTry the option apply actuals
Try the option apply actuals and update progress. You have to have rights to actuals also check your rights also
Member for
12 years 9 monthsRaul,Are you updating? Can
Raul,
Are you updating? Can you show the screen shot? Let's see what I can help.
Warren
Member for
12 years 7 monthsI think I'm having the same
I think I'm having the same problem. I move the data date, run "update progress" and the activies highlighted move out in time to the new DD. It doesn't do this on all projects but just one right now.
ANY advise on what to configure to get this working correctly again will be GREATLY appreciated.