Update Progres option in P6 vs Update Progress option in P3

Member for

13 years 2 months

Try the option apply actuals and update progress. You have to have rights to actuals also check your rights also

Member for

12 years 9 months

Raul,

Are you updating? Can you show the screen shot? Let's see what I can help.

Warren

Member for

12 years 7 months

I think I'm having the same problem.  I move the data date, run "update progress" and the activies highlighted move out in time to the new DD.  It doesn't do this on all projects but just one right now.

 

ANY advise on what to configure to get this working correctly again will be GREATLY appreciated.