right click on gant chart ----- choose 'Bars' ---- find the column named 'timescale' ----- change whatever is chosen into 'project baseline' (same row as project baseline)
cheers
Member for
14 years 11 months
Member for14 years11 months
Submitted by Walid Lahiani on Thu, 2012-01-19 11:48
Member for
14 years 11 monthsGood morning,I did right
Good morning,
I did right click,bars,i checked primary baseline,so I had the bar target graphic
thanks,
Member for
13 years 10 monthsright click on gant chart
right click on gant chart ----- choose 'Bars' ---- find the column named 'timescale' ----- change whatever is chosen into 'project baseline' (same row as project baseline)
cheers
Member for
14 years 11 monthsYes,In Project->Assign
Yes,
In Project->Assign baseline->My choice was current project and now I changed it to Target which I did with Project->maintain baseline
Thank you
Member for
15 years 11 monthsWalid, You might have
Walid,
You might have assigned the current project as your baseline.
Please investigate.....