Why the baseline project start change when I do F9

4 replies [Last post]
walid Lahiani
User offline. Last seen 7 years 37 weeks ago. Offline
Joined: 6 Nov 2010
Posts: 45
Groups: None

Good morning,

Normaly ,baseline dates don't change when we update!?

Thanks

Replies

walid Lahiani
User offline. Last seen 7 years 37 weeks ago. Offline
Joined: 6 Nov 2010
Posts: 45
Groups: None

Good morning,

I did right click,bars,i checked primary baseline,so I had the bar target graphic

thanks,

Forrest Chen
User offline. Last seen 7 years 39 weeks ago. Offline
Joined: 29 Dec 2011
Posts: 10
Groups: None

right click on gant chart ----- choose 'Bars' ---- find the column named 'timescale' ----- change whatever is chosen into 'project baseline' (same row as project baseline)

cheers

walid Lahiani
User offline. Last seen 7 years 37 weeks ago. Offline
Joined: 6 Nov 2010
Posts: 45
Groups: None

Yes,

In Project->Assign baseline->My choice was current project and now I changed it to Target which I did with Project->maintain baseline

 

Thank you

Raymund de Laza
User offline. Last seen 30 weeks 6 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Walid,

You might have assigned the current project as your baseline.

Please investigate.....