Why the baseline project start change when I do F9

Member for

14 years 11 months

Good morning,

I did right click,bars,i checked primary baseline,so I had the bar target graphic

thanks,

Member for

13 years 10 months

right click on gant chart ----- choose 'Bars' ---- find the column named 'timescale' ----- change whatever is chosen into 'project baseline' (same row as project baseline)

cheers

Member for

14 years 11 months

Yes,

In Project->Assign baseline->My choice was current project and now I changed it to Target which I did with Project->maintain baseline

 

Thank you

Member for

15 years 11 months

Walid,

You might have assigned the current project as your baseline.

Please investigate.....