Yes, Am not aware of any other issues. So by populating the Expected Finish datem scheduling option automatically calculates the remaining duration & computes accordingly. So by this means, your Finish Date also will be accordingly updated.
Please let me know if this is not what you meant. Thanks!
Yes, Am not aware of any other issues. So by populating the Expected Finish datem scheduling option automatically calculates the remaining duration & computes accordingly. So by this means, your Finish Date also will be accordingly updated.
Please let me know if this is not what you meant. Thanks!
Member for
19 years 7 months
Member for19 years7 months
Submitted by Frederic Fasquelle on Thu, 2012-03-29 15:00
Member for
13 years 7 monthsI would like to know how to
I would like to know how to copy the budgeted units activity wise on a weekly timescale in P6
Member for
14 years 11 monthsYes, Am not aware of any
Yes, Am not aware of any other issues. So by populating the Expected Finish datem scheduling option automatically calculates the remaining duration & computes accordingly. So by this means, your Finish Date also will be accordingly updated.
Please let me know if this is not what you meant. Thanks!
Member for
14 years 11 monthsYes, Am not aware of any
Yes, Am not aware of any other issues. So by populating the Expected Finish datem scheduling option automatically calculates the remaining duration & computes accordingly. So by this means, your Finish Date also will be accordingly updated.
Please let me know if this is not what you meant. Thanks!
Member for
19 years 7 monthsHi Somasundaram K,I jump of
Hi Somasundaram K,
I jump of your proposal and I would be interested to get any feedback.
To update my project, I am filling "Expected Finish" field (only activity started).
First consequence is to get FF=0 on this activty.
Is there any other consequence in scheduling ?
Is it a good practice to fill this field instead of modifying directly finish date ?
regards
Member for
14 years 11 monthsSchedule using Expected
Schedule using Expected Finish date field. That should solve your problem. Thanks!