P6 Calculation fixed unit/Time

Member for

13 years 7 months

I would like to know how to copy the budgeted  units activity wise on a weekly timescale in P6

Member for

14 years 11 months

Yes, Am not aware of any other issues. So by populating the Expected Finish datem scheduling option automatically calculates the remaining duration & computes accordingly. So by this means, your Finish Date also will be accordingly updated.

Please let me know if this is not what you meant. Thanks!

Member for

14 years 11 months

Yes, Am not aware of any other issues. So by populating the Expected Finish datem scheduling option automatically calculates the remaining duration & computes accordingly. So by this means, your Finish Date also will be accordingly updated.

Please let me know if this is not what you meant. Thanks!

Member for

19 years 7 months

Hi Somasundaram K,

I jump of your proposal and I would be interested to get any feedback.

To update my project, I am filling "Expected Finish" field (only activity started).

First consequence is to get FF=0 on this activty.

Is there any other consequence in scheduling ?

Is it a good practice to fill this field instead of modifying directly finish date ?



regards

Member for

14 years 11 months

Schedule using Expected Finish date field. That should solve your problem. Thanks!