Oracle Primavera - PM6 Member for 21 years 11 months Member for 21 years 11 months Submitted by Stephen Phillips on Thu, 2012-07-26 09:56 Permalink Thanks. Sussed it out Thanks. Sussed it out eventually - needed to clear the expected finish date. Member for 18 years Member for 18 years Submitted by Rony Roberto on Thu, 2012-07-26 09:39 Permalink may be your actual finished may be your actual finished date is earlier that actual start date. Log in or register to post comments
Member for 21 years 11 months Member for 21 years 11 months Submitted by Stephen Phillips on Thu, 2012-07-26 09:56 Permalink Thanks. Sussed it out Thanks. Sussed it out eventually - needed to clear the expected finish date.
Member for 18 years Member for 18 years Submitted by Rony Roberto on Thu, 2012-07-26 09:39 Permalink may be your actual finished may be your actual finished date is earlier that actual start date.
Member for
21 years 11 monthsThanks. Sussed it out
Thanks.
Sussed it out eventually - needed to clear the expected finish date.
Member for
18 yearsmay be your actual finished
may be your actual finished date is earlier that actual start date.