Oracle Primavera - PM6 Member for 21 years Member for 21 years Submitted by David Kelly on Wed, 2011-12-14 13:48 Permalink Copy the baseline you want Copy the baseline you want the dates from (P6 v7 lets you do this in place) Restore the baseline to the live EPS Open the project you just restored Run a global change to set : Planned start = Late Start Planned Finish = Late Finish Demote the project to being a baseline again Use that baseline - set it as secondary or tertiary - and as with ALL BASELINES it uses the planned dates to draw a bar. Member for 18 years 3 months Member for 18 years 3 months Submitted by Ferdinand U. on Tue, 2011-12-13 05:15 Permalink you can try to create UDF for you can try to create UDF for late bar using excel import/export copied from your baseline late dates Member for 18 years 3 months Member for 18 years 3 months Submitted by Ferdinand U. on Tue, 2011-12-13 05:15 Permalink you can try to create UDF for you can try to create UDF for late bar using excel import/export copied from your baseline late dates Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Mon, 2011-12-12 20:10 Permalink Ayman,I am afraid there is no Ayman, I am afraid there is no early and late baseline bars in P6 as there was in P3; as far as I know, P6 only manages early bars when you maintain and assign baselines Alexandre Log in or register to post comments
Member for 21 years Member for 21 years Submitted by David Kelly on Wed, 2011-12-14 13:48 Permalink Copy the baseline you want Copy the baseline you want the dates from (P6 v7 lets you do this in place) Restore the baseline to the live EPS Open the project you just restored Run a global change to set : Planned start = Late Start Planned Finish = Late Finish Demote the project to being a baseline again Use that baseline - set it as secondary or tertiary - and as with ALL BASELINES it uses the planned dates to draw a bar.
Member for 18 years 3 months Member for 18 years 3 months Submitted by Ferdinand U. on Tue, 2011-12-13 05:15 Permalink you can try to create UDF for you can try to create UDF for late bar using excel import/export copied from your baseline late dates
Member for 18 years 3 months Member for 18 years 3 months Submitted by Ferdinand U. on Tue, 2011-12-13 05:15 Permalink you can try to create UDF for you can try to create UDF for late bar using excel import/export copied from your baseline late dates
Member for 22 years 9 months Member for 22 years 9 months Submitted by Alexandre Faul… on Mon, 2011-12-12 20:10 Permalink Ayman,I am afraid there is no Ayman, I am afraid there is no early and late baseline bars in P6 as there was in P3; as far as I know, P6 only manages early bars when you maintain and assign baselines Alexandre
Member for
21 yearsCopy the baseline you want
Copy the baseline you want the dates from (P6 v7 lets you do this in place)
Restore the baseline to the live EPS
Open the project you just restored
Run a global change to set :
Planned start = Late Start
Planned Finish = Late Finish
Demote the project to being a baseline again
Use that baseline - set it as secondary or tertiary - and as with ALL BASELINES it uses the planned dates to draw a bar.
Member for
18 years 3 monthsyou can try to create UDF for
you can try to create UDF for late bar using excel import/export copied from your baseline late dates
Member for
18 years 3 monthsyou can try to create UDF for
you can try to create UDF for late bar using excel import/export copied from your baseline late dates
Member for
22 years 9 monthsAyman,I am afraid there is no
Ayman,
I am afraid there is no early and late baseline bars in P6 as there was in P3; as far as I know, P6 only manages early bars when you maintain and assign baselines
Alexandre