Set up a calendar that has one work day in a six week period of non work days and apply it to your "Meeting" task - the duration should be the number of anticipated meetings.
Make sure you add progress to block out the meetings as and when they occur.
Member for
19 years 10 monthsHi Jane Set up a calendar
Hi Jane
Set up a calendar that has one work day in a six week period of non work days and apply it to your "Meeting" task - the duration should be the number of anticipated meetings.
Make sure you add progress to block out the meetings as and when they occur.
Best regards
Mike Testro