Recurring activity in P6

Member for

19 years 10 months

Hi Jane

Set up a calendar that has one work day in a six week period of non work days and apply it to your "Meeting" task - the duration should be the number of anticipated meetings.

Make sure you add progress to block out the meetings as and when they occur.

Best regards

Mike Testro