Automatic changing of the Data Date in PM6

Member for

12 years 5 months

Hi Eric,

 

I'm also encountering your problem which is really frustrating coz after i plotted dates to all activities and press F9 they get back to their previous dates or to the data date. I checked out the the check box mentioned by Rajesh but same as you, the check box is currently unchecked and is uncheckable. 

I aslo imported this file from MS project. Could this be something with the MS project? 

 

Russell

 

Member for

15 years 9 months

Eric,

Good Info

I want to use this setting of 'Set Data Date and Planned Start Date to Project Forecast Start Date during Scheduling'.

But the option now is unchecked and it is not possible to check it.

so where can i change it.

 

Rgds

Member for

19 years 1 month

Eric,

Under Tools/ Schedule, there is a check box - 'Set Data Date and Planned Start Date to Project Forecast Start Date during Scheduling'. Make sure that it is unchecked. I can only think of this option.

Let me know if it works.

Thanks,

Rajesh