If you are copying a project dont paste into the same project as it cant create the same activity ID in your new wbs. Try to paste it in the EPS name and not the project itself by highligting the EPS name then click paste.
Cheers
jash
Member for
18 years 9 months
Member for18 years9 months
Submitted by Dieter Wambach on Mon, 2011-08-01 11:46
After this action the size of your projects would exceed the size of your database. If you have no own Oracle or MS SQL Server a light version will be installed automatically together with P6.
Member for
15 years 10 monthsHi Ronnel, If you are copying
Hi Ronnel,
If you are copying a project dont paste into the same project as it cant create the same activity ID in your new wbs. Try to paste it in the EPS name and not the project itself by highligting the EPS name then click paste.
Cheers
jash
Member for
18 years 9 monthsRonnelAfter this action the
Ronnel
After this action the size of your projects would exceed the size of your database. If you have no own Oracle or MS SQL Server a light version will be installed automatically together with P6.
Delete projects or baselines, then it will work.
Regards
Dieter